Willard Water District Improvement Project – Update June 8, 2024

Construction has resumed on the project with the focus on County Road 132A.

The current portion of the project involves installing the new water main (ductile iron and HDPE plastic) along County 132A and then connecting services. During the previous week:

  • Ductile iron pipe section going north along County Road132A was installed, tested, and approved.
  • Approximately 1,000 feet of the HDPE is bored, and the pipe is fused for installation next week.

One item of note: an old section of main on County Road 132A was leaking and was repaired. One resident had their service switched over to the new line due to the spot of the break.

Work scheduled for the week of June 10 through June 14:

  • Pull the HDPE through the bore and test.
  • Finish the final 400 feet of boring and pipe installation.
  • Start connecting services on County Road 132A.