Willard Water District Improvement Project Update – August 28, 2023
Work on the project is continuing at a fairly rapid pace. Last week, from Tuesday to Thursday, approximately 800 linear feet of pipe was installed which represents almost 10% of the total. One fire hydrant was also installed.
During this week, construction crews expect to install the remainder of the hydrants on the 800 feet of line that has been completed. In addition, work will continue along Main Street with the installation of more water main.
The weather has remained relatively cooperative, and we hope to continue the project without any significant interruptions. We are still on schedule to complete the installation portion of the project before the end of this calendar year, with testing to follow right behind.
We will post additional updates as they are available.